San Martin Construction Update – March 14, 2016

  • San Martin Drive closures remain in place.  A flagger will be posted at the San Martin Center for the foreseeable future to assist motorists who try to approach the road closure and coordinate deliveries through the West Gate intersection.
  • Tree protection measures, tree pruning, and sediment & erosion control have all been completed.  Installation of utility structures is ongoing.
  • Two test micropiles were installed this week and will be load tested next week.  Production micropiles for the bridge will start at the end of next week.  Micropile installations will continue for approximately the next month.
  • Granite curbs will be onsite in 2 weeks, which will drive the schedule for sidewalk operations.
 
 
 