San Martin Project Update

San Martin Construction Update – April 6, 2016

  • San Martin Drive closures remain in place.  A flagger continues to be posted at the San Martin Center to assist motorists.
  • Micropile installations for the new bridge are continuing.  All micropiles on the south end have been installed; micropiles on the north end will continue through the month.
  • Granite curbs and some concrete curbs have been installed at the Bowman Drive intersection.  Granite curbs for the Wyman Park Drive intersections are starting to go in now.
  • Concrete for the Wyman Park intersection feature wall has been placed.
  • Installation of the retaining wall between the new bridge and San Martin Center will begin next week.
  • Electricians are working their way north from the Wyman Park Drive intersection with installations of lighting and associated structures.
  • Work on Saturday, 4/9 (weather permitting) will include excavation for retaining walls south of San Martin Center, and granite curb installation at Wyman Park Drive intersection.
 
 
 