San Martin Construction Update – May 6, 2016

  • San Martin Drive closures remain in place.  A flagger continues to be posted at the San Martin Center to assist motorists.
  • Micropile installations for the new bridge have been completed.  Bridge steel installation will begin this week.
  • Granite and concrete curb installations at the Bowman Drive and Wyman Park Drive intersections are continuing.  Concrete base has been poured for the Bowman Drive intersection.
  • Excavations for the retaining wall between the new bridge and San Martin Center are complete.  Retaining wall construction will continue over the next two months.
  • Electricians are continuing to work their way north, near Olin Hall and north of the new bridge, with installations of lighting and associated structures.
  • Phase 1 closures are expected to continue through the end of August.  Phase 2, including the closure of the northern end of San Martin Drive will begin around September.
 
 
 