Project Description

The Wyman Park Building renovation consists of constructing a new building core addition with new elevators and a multi-floor communicating stair. New rooftop mechanical equipment, interior and exterior renovations, including masonry cleaning and repointing, select window replacements, and a roof replacement, will also be included.

Project Schedule

Mobilization Fall 2021
Core Addition Ground Work Begins Fall 2021
Remove Roof AHUs Summer 2022
Core Addition Topping Out Fall 2022
Existing Loading Dock Repairs Spring 2023
Project Completion Winter 2023

Project Team

Chuck Hilseberg, senior project manager

Project Logistics

Traffic/Pedestrian Closures & Detours

  • Construction traffic to enter/exit the site at 31st St.: right on Remington Ave., left on Wyman Park Dr. to Sisson St./29th St./I-83
  • Construction workers will park at Johns Hopkins at Eastern on 33rd St. and will be shuttled to the job site daily